Project: Holiday Inn - Rosslyn
Date: 12.13.2020
CLOSE
Clearing the Way
CDI, acting as Explosives Subcontractor to Main Demolition Contractor, The Berg Corporation of Baltimore, Maryland, performs the preparation for and explosives felling of one (1), 20-story, post-tensioned, reinforced concrete hotel structure in Rosslyn, Virginia on Sunday, December 13, 2020.
CDI performed the emergency preparation for and the explosives felling of the he damaged, 480’ tall guyed structure in less than three (3) hours on Monday, November 16, 2020.
CDI, acting as the Explosives Subcontractor to Main Demolition Contractor, The Berg Corporation of Baltimore, Maryland, performed the preparation for and successful explosives felling of four (4), 400’ tall radio towers in Bethesda, Maryland on Wednesday, November 4, 2020.
CDI performed the explosives felling of the two-way clear span truss roof system of the Palace Arena in Auburn Hills, Michigan at 8:00 AM on Saturday, July 11, 2020.